CREW configura BARGES P10

Orientações Gerais de Uso

Um mínimo 100 ton guindaste é necessário para carregar fora das barcaças do caminhão para a água. Each barge has a single lifting clevis or shackle in the top of the barge for easy loading and unloading. Poseidon® 1 -10’ x 40’ x 5’ barges weigh 23,500 lbs. Poseidon® 2 -10’ x 40’ x 5’ Sectional Barges weigh 23,700 lbs.  each and Poseidon® 3 Barges weigh 23,700 lbs. each. Tag lines should be attached to the ends of the barges to control the movement of the equipment while in the air. After pulling the barges together, have a couple of men stand on the outside of the barges in order to cause the barge to come together at the bottom. An alternate method is to thread a small choker through the rope thimbles on both barges and lift up slightly with the crane. Once the bottom is together, carefully drop the 55 lb. pin in place being careful not to pinch your fingers.

The Poseidon® 1

barge has a Rendrag® compatible connection system. Hairpin connectors are dropped into position. The 40’ x 10’ x 5’ barges are equipped with 8 connection points on the sides and 2 connection points on the end. Each 40’ x 10’ x 5’ barge can support 35,000 lbs at a 2’6” draft. Rope thimbles on the sides and ends of the barges are used to assist in pulling the barges together prior to pinning.

The Poseidon® 2

barge has a Flexifloat® compatible connection system. The internal locking clasp is pried up with a lifting bar. The barges are pulled together using ropes in the rope thimbles. An alternative method would be to run a small choker through both rope thimbles and lift up slightly with the crane. This will draw the bottom of the barges together. The barges need to be near touching before the locking bar will drop down at the top or the bottom. The locking clasp may be tapped into the locked position with a small hammer.

The Poseidon® 3

barge is Shugart® compatible. The P3 barge has a set of upper and lower angles on the sides and ends of the barge. There are 32 pin holes on the 41’4″ length and 8 pin holes on the 10’4″ end. The P3 barges must be assembled so that the narrow side angles fit above and below the wider side angles on he opposing barge. Line up and secure the pin on the end of the barge, then fold the barge together against the opposing barge, drop the pins into the angles beginning at the opposite end.

Use of Hardwood Mats on Poseidon Barges

The contractor must supply and use oak or yellow pine 8" - 12" crane mats when using cranes, excavators or any other pieces of equipment with steel crawler tracks or rubber tire equipment. Below are examples of damage that has occured to barges when they are not used properly. The sides, ends& bottom skin surface of the barge is made of A-36 1/4” steel plating. The tops are covered with a skid resistant 11 gauge patented roll form material. Damage to the barges on the project will be repaired and invoiced back to the contractor. Pictures of the damages will be taken along with an estimate of the repairs prior to the work being completed for the contractor’s review. Below is a sampling of pictures from damaged equipment returned after the project.

DAMAGE:

Any defect that structurally impairs or degrades the equipment in its ability to perform the intended function and duty including, but not limited to, providing flotation for construction equipment. Or, any defect that materially degrades the commercial resale value of the equipment, beyond an amount typically expected based upon the duration, duty cycle, and type of work performed during the rental period.

Specific Damage Criteria for Equipment Sides, Ends, Decks, or Bottoms:

  • Any structural member deformed by ¼” or greater. (Angle, channel, formed pocket, casting, rope thimble)
  • Any plate section deformed by ½” or greater, regardless of size of defect
  • Any plate section deformed by ¼” or greater when defect distribution is 20% ou mais de área quadrada painel. (Veja a ilustração abaixo).
  • Qualquer furo ou rasgo onde o material de aço é perfurada é considerado danos.

EXEMPLO DE CÁLCULO DANOS AVALIAÇÃO: 20% PAINEL DE ÁREA DE REGRA

As fotos e ilustrações DE DANOS EXEMPLO

Laminado de topos ou lavá-embarque ocorre como um resultado de não usar esteiras de madeira. cantos danificadas e painéis de extremidade ocorreu quando os lados e extremidades da barcaça foram atingidos com um balde de escavadora ou com os joelhos do impulso do rebocador. os topos, laterais e extremidades destes barcaças foram substituídos e os custos foram passados ​​para o contratante. A placa exterior é cortado e removido juntamente com ângulos interiores danificadas e estrutura. As peças de reposição são soldadas no lugar, revestido com inibidor de ferrugem bio-float no interior e o exterior é jateado e pintado com um primer de uretano Baril rico em zinco e um acabamento de poliúria alifática de baixo brilho.Assim que o seu operador atinge o lado da barcaça com o balde escavadeira ou uma pedra ou outros detritos pesado cai no convés barcaça causando um dente, parar imediatamente, tirar fotos dos danos, documente a data e a hora em que ocorreu o incidente e comunique o dano à sua seguradora. Você deve fornecer uma data específica of ocorrência à seguradora para cobertura do dano.O operador deve ser orientado sobre o uso adequado do equipamento para não repetir os danos novamente. Notificar tambémPoseidon® Barcaça do dano.

O contratante pode soldar ferro de ângulo adicional, braçadeiras, etc. para proteger qualquer equipamento nas barcaças.Poseidon® A barcaça exige que esses itens sejam removidos e os fragmentos remanescentes retificados até a superfície original antes de devolver a barcaça no final do período de aluguel. Pinte a área do solo com spray vermelho / Brown Rustoleum pintura.

Spuds and pockets are available to secure the barge in position on the water.Spuds should be supported by two chokers or nylon straps rated to lift 10,000 pounds or more prior to the truck driver removing the chains or straps securing the spuds to the truck bed. Isto irá assegurar que eles não rolar para fora ou deslizar para fora do caminhão com expectativa. Batatas são rebaixada para a superfície do fundo do lago, lagoa ou rio e empurrado para dentro da lama abaixo. The barges can also by tied off by rope or cable through the thimbles on the sides or ends of the barges or by using the cleats supplied by Poseidon® Barge.

Do not pound on the top of the spud with an excavator bucketas this will damage the spud. Repairs to the spud due to such activity will be charged back to the contractor. Spuds can be raised and lowered by a crane line or by a hydraulic winch. Poseidon® Barge offers double drum winch units for sale or for rent. 5/8” Steel cable is tied off on the outside of the spud pocket on the lifting eye, threaded through the 20” sheave at the bottom of the spud and then brought up through the spud pocket and attached to the winch. If you run steel cable from the barge or winch across the body of water you are working on to the shore, bright orange vinyl ribbons should be hung from the cable, making it visible to any water craft that is operating in the vicinity.

Rental Rates do not include insurance on the barges. A Certificate of Insurance naming Poseidon Barge, Ltd as “Additional Insured” under your general liability policy, plus listing us as a “Loss Payee” under your equipment floater policy for dual protection against physical damage must be supplied, prior to shipping the barges to your job site. Additional details and requirements are included with our quote and lease agreement.

Adequate trainingfor operating the equipment, transported and used on the barges is the contractor’s responsibility. Poseidon® Barge, Ltd are not liable for any accidents due to operation of equipment on the barges under any circumstances including unsafe weather conditions, such as high winds, thunder storms, heavy rains, high wake, and icy or heavy snow conditions or any other hazardous weather conditions.  Normal loading, unloading, dredging processes, and high humidity in the air may cause water to pool on all working surfaces on the barges. Care must be taken by equipment operators and workers to ensure the safety of the workers and equipment. Life vests should be worn at all times when working around the water. In sub-freezing air temperatures, ice will form on the barges and crane mats. It is the contractors responsibility to take any and all precautions in safe guarding their employees as well as the general public.

Minimum width necessary to float equipment.Poseidon® does not recommend floating a 25-30 ton excavator on a platform less than 30′ wide (3 sections 40′ x 10′ x 5′ wide).  Adicionalmente, if you are performing dredging work in hard digging conditions, Poseidon® also recommends a minimum of 4 spuds and pockets to minimize possible damage to the spuds & pockets as a result of the pulling energy caused by the bucket in hard soil conditions. If the contractor observes that Poseidon® equipment is getting dented up, spud pockets are being pulled apart, and or spuds are getting bent as a result of the excavator being too large for the platform, soil conditions are too hard or the operator is using the equipment in a careless manner, it is the contractors responsibility to change the parameters of the project and find an alternative method to complete the project. The contractor is responsible for all damages to the equipment. Just because our barges will float your equipment does not mean they can withstand the additional abuse as a result of difficult & hard digging conditions.

Poseidon® Barge offers static stability analysis for the use of floating cranes. Our analysis is only as good as the information provided. Knowing the make and model of the crane, o comprimento da lança, o raio você vai trabalhar com o guindaste, o peso picareta e o peso e tipo de equipamento adicional que será flutuando na barcaça vai ajudar a nossa equipe para fazer recomendações adequadas.

Antes de devolver o equipamento, todo o crescimento marinho e sujeira devem ser limpos das barcaças.crescimento marinho inclui cracas, briozoários, moluscos, poliqueta e outros vermes tubulares, mexilhão zebra, algas marinhas, algas & qualquer outro tipo de sujidade ou lama na superfície da barcaça. Você pode ter que raspar as barcaças e limpá-las com vapor para eliminar qualquer material restante na barcaça. E sePoseidon® tem que limpar novamente o equipamento, as taxas de limpeza serão facturados de volta para o contratante.

Toda a água de lastro e água acumulada devido à condensação deve ser removida das barcaças antes de retirá-las da água e carregá-las no caminhão.Água dentro da barcaça fará com que a carga fique acima do peso. A barcaça não vai se levantar uniformemente para fora da água, pois há um único ponto de içamento na parte superior central da barcaça. Além disso, mover a água dentro da barcaça pode fazer com que a barcaça mude de posição no caminhão se o motorista tiver que parar rapidamente. A água pode ser expelida usando um compressor de ar e os bujões de lastro de água nos cantos superiores da barcaça. It can also be pumped out or if necessary, cut a 2” hole on the sides of the barge towards the end approximately 3” from the bottom to drain the water out prior to shipping. Please notify us when doing this, so that we can anticipate the repairs. The Poseidon® Barge system is designed for easy handling and economical transportation to and from your project.

Poseidon® Double Drum WinchDaily maintenance and inspections should be done to assure safe operation. Oil levels should be checked daily. The key is located on the dip stick when you first receive the unit. The engine should be started and allowed to idle for a minimum 30 minutes to allow the hydraulic oil to heat up. Operating hydraulic equipment with cold hydraulic oil could cause seals to break resulting in hydraulic oil spills. We use 46 weight Clarity Oil in our equipment to minimize environmental impact. Wire cable is not supplied by Poseidon® with the winch. All cable is to be removed prior to returning the winch and the fuel tank should be filled up. Tape the wedges to the drums using duct tape.

Poseidon Sea BeesA manutenção e inspeções diárias devem ser feitas para garantir uma operação segura. Os níveis de óleo devem ser verificados diariamente. As unidades devem ser iniciadas e permitidas em marcha lenta por um mínimo de 30 a 90 minutos para permitir que o óleo hidráulico aqueça dependendo da temperatura do ar. Os níveis de óleo devem ser verificados diariamente. As mangueiras devem ser verificadas visualmente para garantir que não haja dobras ou vazamentos nas mangueiras. Se você acertar a hélice em uma rocha ou árvore, pare a unidade imediatamente e inspecione o suporte quanto a danos. Isso pode fazer com que a vedação do motor hidráulico no alojamento da hélice quebre ou dobre o eixo da hélice. Se isso ocorrer, the 8″ steel tube shaft will fill up with hydraulic oil. If you notice oil leaking out of the top of the steel shaft, shut down the unit immediately and call Poseidon® to make arrangements for a repair.

Winch Units & Barge Pusher Units should be secured with four long chokerspreso aos suportes nas estruturas das unidades e apoiado pela linha do guindaste antes do motorista do caminhão remover as correntes ou correias que prendem as unidades ao caminhão. Isto irá assegurar que as unidades não deslocar ou cair fora do caminhão expectativa causando danos ao equipamento ou ferimentos para o pessoal de terra. As unidades devem permanecer nível como eles estão sendo tirado do caminhão.